F-35 - News and Discussions | Page 19 | World Defense

Khafee

Administrator
Staff member
Joined
Nov 17, 2017
Messages
12,324
Reactions
24,465 1,293 0

Khafee

Administrator
Staff member
Joined
Nov 17, 2017
Messages
12,324
Reactions
24,465 1,293 0

Australia spent billions on jet fighters off the plan. Now, we’re having trouble even flying them

Published: March 3, 2022


There’s a problem with Australia’s brand new fighter jet – it’s just not that reliable. As a result, it flies about 25% less than it should. Less flying means fewer well-trained pilots, but it also hints at other problems lurking in the background.

Everybody who buys a house or apartment off the plan knows there may be some surprises along the way. Australia’s fighter jets are the same.

Why Australia bought these jets

Australia committed to its new F-35 fighters off the plan in 2002. At the time, the F-35 was still a twinkle in the eyes of Lockheed Martin’s marketers. The US and several European countries had commissioned the aerospace company to design, build and manufacture the F-35, with the first step being a prototype.

Australia’s plan was to buy four squadrons – about 72 jets in total – at a cost of around A$16 billion. The F-35 was intended to replace the air force’s ageing Hornet fighters and F-111 bombers. And back in 2002, when Middle East wars were raging, a short-range stealth fighter seemed more than adequate.

But by 2010, with China firmly on the rise, it became apparent this was a poor strategy. In retrospect, a key error was looking at the F-35 simply as a replacement aircraft without first assessing the changing strategic environment. But by then, too much money had been sunk into the F-35 program to change course.

Then, the F-35 development ran late, and the first tranches of Australia’s fleet weren’t ready to be deployed on operations until December 2020.

Escalating problems

Building the aircraft proved harder than anticipated and this inexorably fed into higher costs.

Much of the money that should have been spent on building the maintenance support system went into trying to fix the aircraft’s continuing hardware and software problems. Accordingly, there are now fewer depots to fix broken parts and fewer spare parts than there should be.
Little of this is in Australia’s control. America’s global support solution (GSS) is used to keeping Australia’s F-35 fleet flying. The GSS manages spare parts, maintenance, supply chain support, training systems and engineering. But the program is new, creating problems both now and into the next decade.



There was a second compounding problem arising from the drawn-out development process: the F-35 jets were constructed at different times over the past ten years in seven different configurations. Think about the maintenance staff having to repair individual aircraft in a large fleet with no single standard configuration. Every repair is an adventure – and a learning experience.

The configuration complexity, insufficient spare parts and slow spare part repair times mean there are fewer serviceable aircraft on the flight line now than was expected even a couple of years ago.

In 2019, the Department of Defence estimated the F-35 fleet would fly 11,800 hours in the fiscal year 2021-22. The real figure, however, is 3,000 hours below that.

In simple terms, Australia is short the flying hours needed to keep a squadron’s worth of pilots combat ready. This is very worrying, as Australia only has three operational F-35 squadrons in total.

Continuous upgrades at tremendous cost

A perfect solution to this is probably not possible. For example, the two F-35 aircraft Australia bought in 2013 for more than A$280 million are now arguably too old to be upgraded to the current configuration. In terms of flying combat missions, these two aircraft are obsolete.

The US Air Force frets its similarly old F-35s are now just crushingly expensive training aircraft.

Most of Australia’s fleet is planned to be upgraded to be broadly similar to the US fleet, although this will cost even more money. It may seem strange to have to pay extra to upgrade a brand new aircraft on delivery, but that’s not the end of the problems. There is another complication.
Australia’s latest F-35s (as well as the upgraded older ones) use the Block 3F software, a digital operating system designed by Lockheed Martin. It is proving to be just as costly to keep updated as the jets themselves.

Lt. Gen. S. Clinton Hinote, the US Air Force’s deputy chief of staff, has serious concerns about the outdated software, saying last year,
the block that is coming off the line right now is not a block that I feel good about going up against China and Russia.
He noted recent war games focused on the prospect of defending Taiwan from Chinese air attack showed
Every [F-35] that rolls off the line today is a fighter that we wouldn’t even bother putting into these scenarios.
This means Australia’s F-35s appear not to be as good as the potential opposition. It seems Australia is paying to lose the air combat battle.

The only solution: another upgrade

So, what is the solution to these seemingly intractable and eye-wateringly expensive problems?

Lockheed Martin is advocating a major operating system software upgrade: the Block 4. It might not be surprising to hear this is now running years late, with delivery expected in 2027 or later. It is also significantly over budget.

In a small piece of good news, the last nine F-35 aircraft Australia will get off the production line next year, and may be partly Block 4 compatible. Hinote thinks these F-35s might be capable of fighting against first-rate adversaries.



The bad news is the full Block 4 upgrade now requires a major engine upgrade or even a new engine. So, this means Australia’s current F-35 fleet might not be able to use all the Block 4 software until after 2030 – and at a substantial cost.

Buying another hugely expensive upgrade for a brand new fighter is actually the cheap way out. The US Air Force’s focus is already shifting to the Block 4 upgraded aircraft. Countries like ours with older F-35s will be left to fend for ourselves if we don’t embrace the new technology, as well.
But the costs do keeping going up, and the problems with these F-35 jets haven’t seemed to stop. It’s the price of buying off the plan, which anyone who’s bought a house or apartment would surely know.
 

Khafee

Administrator
Staff member
Joined
Nov 17, 2017
Messages
12,324
Reactions
24,465 1,293 0

Germany to buy F-35 warplanes for nuclear deterrence

By Sebastian Sprenger

Tuesday, Mar 15

WASHINGTON – Germany will buy up to 35 copies of the U.S.-made F-35 fighter jet, reversing years-long plans that saw the fifth-generation warplane eliminated from consideration, defense leaders announced Monday.

The planes will take over by 2030 the niche, but crucial, nuclear-weapons mission from the aging fleet of Tornado aircraft, Defense Minister Christine Lambrecht said during a joint statement with Air Force Chief of Staff Lt. Gen. Ingo Gerhartz in Berlin.


The decision means Germany will continue to provide suitable aircraft for carrying U.S. nuclear weapons stored in the country into a hypothetical atomic battle, as prescribed under NATO doctrine. Previously, officials were planning to buy new versions of the the F-18 for that role plus the job of electronic attack and suppressing enemy air defenses.

The Tornado-replacement decision, talk of which has amounted to a parlor game in Berlin policy circles for more than a decade, removes the Super Hornet from the table altogether, instead positioning a modernized Eurofighter aircraft as the weapon of choice for electronic combat. That line of thinking is sure to please manufacturer Airbus, which had all along proposed its plane as a kind of sandbox platform leading to the French-German-Spanish Future Combat Air System by 2040.

The decision in favor of the F-35 comes in the context of Germany’s defense strategy adjustment following Russia’s assault on Ukraine. Berlin’s new spending and modernization plans prize off-the-shelf systems that can quickly plug readiness holes in the armed forces.


“There is only one response to [Russian President Vladimir] Putin’s aggression: unity within NATO and a credible deterrent,” Gerhartz said. “That’s why there is no alternative to the decision in favor of the F-35.”

Gerhartz and Lambrecht touted cooperation opportunities surrounding the Lockheed Martin-made plane, which other European nations have already bought or plan to buy. Most recently, Switzerland and Finland picked the stealthy aircraft to replace legacy warplane fleets. The U.K., the Netherlands, Belgium, Italy, Denmark and Norway also are among the customers on the continent.

Meanwhile, Germany remains committed to the FCAS program, according to a German Defense Ministry statement. Lambrecht said she had told her French counterpart, Florence Parly, about the F-35 decision during at March 9 visit to Evreux Air Base in northern France, where the two countries are operating a joint air-transportation unit built around C-130J aircraft.

A spokesperson at the French Ministry of Defence was not immediately available for comment.


The FCAS program is at a critical juncture, as key contractors Dassault and Airbus Defence and Space are unable to reach an agreement covering workshare and intellectual property rights for the futuristic program’s central fighter jet.

Earlier this month, Dassault CEO Eric Trappier spoke dismissively about the prospect of Germany buying the F-35, suggesting Berlin was being pressured by the United States into buying the jet for the nuclear mission while paying lip service to the mantra of buying European.

With Dassault’s order books filled for its cash cow product, the Rafale plane, the company may have little incentive to compromise on its leadership claims for the next-generation fighter, German analysts have said. Unless, that is, French President Emmanuel Macron intervenes in the spirit of saving the program.
 

Khafee

Administrator
Staff member
Joined
Nov 17, 2017
Messages
12,324
Reactions
24,465 1,293 0

Full weapons tester report highlights F-35 availability, software problems

By Stephen Losey

Mar 17, 2022

WASHINGTON — Lagging availability rates, flareups of new software problems, and a stubborn number of open deficiencies plagued the troubled and repeatedly delayed F-35 fighter in 2021, according to a newly-revealed version of the Pentagon’s weapons tester’s report.

For the first time, the Office of the Director, Operational Test and Evaluation in January only released to the public an “uncontrolled” version of its annual report. Details about shortfalls in key programs were relegated to a “controlled” — but still unclassified — edition kept from the public.


The watchdog group Project on Government Oversight obtained, and last week posted online, the controlled report, which fleshes out some of the problems hinted at in the publicly released version.

Dan Grazier, a military analyst for POGO and a vocal critic of the F-35 program, said in a March 11 interview the Pentagon’s secrecy on this report is troubling and undermines the effectiveness of its testing office.
“The Pentagon did go to really extraordinary lengths to try to hide these details,” Grazier said. “That’s not the way this is supposed to work.”

And in a March 9 post on POGO’s blog, Grazier said the report reveals “stagnation and even backsliding” in some areas used to measure the fleet’s reliability.

Lt. Gen. Eric Fick, program executive officer for the F-35 Joint Program Office, said in a March 8 roundtable with reporters, before POGO posted the full report, that 2021 was “a pretty good year for the program, despite all of the chaos that seemed to surround it.”

He pointed to the 142 F-35s the program delivered in 2021, beating the goal of 139 fighters, as an example of progress — but acknowledged issues remained with engine production and the ability to perform critical simulation tests necessary for a decision on full-rate production.
Some of the F-35′s biggest remaining problems highlighted by the full DOT&E report were:

  • The F-35′s availability is still lagging, and a lack of spare parts and fully-functional engines has hurt it.
The F-35 saw a “program high peak” in aircraft availability in January 2021, the controlled version of the report said, when it hit 70%. But during the year, the report said, availability rates “plateaued,” and in June started to slide before hitting a low of 53% in September. Throughout fiscal 2021, the entire F-35 fleet averaged 61% availability, below its target of 65%. The F-35 has consistently stayed above 50% availability since December 2018.

Of the average 39% unavailable at any given time, 15% were down for maintenance, 16% were waiting on spare parts and another 8% were undergoing depot maintenance.

The report said the progress the F-35 made before June was due to two factors: an influx of new aircraft that didn’t require time in the depots, and a program effort focusing on increasing the availability of spare parts.

That spare parts increase didn’t last, however, and the report said the post-June decline was largely because spare parts weren’t available when they needed. In a newly-revealed passage, the DOT&E report said 15% of the F-35 fleet was sidelined due to a lack of spare parts in May 2021. By December, a full quarter of the fleet was down for that reason.


Grazier wrote on POGO’s site this has very troubling implications for the military’s ability to consistently keep the F-35 ready to fly.
“What that means is the F-35 did not suddenly become a more reliable aircraft in 2021,” Grazier wrote. “It means that it takes extraordinary effort to keep the fleet operating even close to the required levels and suggests that those availability rates are not sustainable long-term.”

Fick acknowledged the drop in F-35 mission capable rates March 9 at the McAleese Defense Programs Conference in Washington March 9, but pledged to address the root causes of the problems that led to that readiness decline, including a shortage of F135 power modules.

Fick also said at the event the F-35 program is taking several actions to improve the health of the fleet, including keeping parts on the aircraft longer, ensuring enough spare parts are on hand when those parts fail, and bolstering repair capacity for a growing fleet.


“No program is perfect, and a program as complex as the F-35 will always have challenges,” Fick said. “But none of these challenges are insurmountable.”

The JPO declined to comment on information from the controlled version of the report.

But that non-public version went into further detail on the shortage of fully functional F135 engines, worsened by a lack of depot repair capacity, that further drove down availability rates. This was particularly felt by the F-35A, the report said.

One week in June, there were 38 F-35s down awaiting a working engine. By the last full week of the fiscal year, there were 52 F-35s waiting for an engine.

The services try to manage the shortage of engines by giving combat-coded units the priority to get spares over test and training units, the report said — but the shortage has nevertheless hit deployed units as well. The U.S. military’s 214 combat-coded F-35s averaged 70% availability throughout 2021, but that number dipped as low as 63% at one point.

After highlighting the progress made in aircraft production in the March 8 briefing, Fick acknowledged the propulsion side was “not quite as great of a story.” The program hoped to deliver 159 engines last year, but only produced 152, all but four of which were late.

Fick said none of the late engines led to late delivery of a production aircraft, but the program is working with Pratt & Whitney to get its engine deliveries back on schedule. Fick said the COVID pandemic — particularly higher rates of absenteeism — had a big effect on the program’s ability to deliver engines on time.
  • Its software programs aren’t being tested properly for hidden bugs — and, in at least one case, a system that was working fine got broken when a new capability was added elsewhere.
The F-35 program’s developmental test teams haven’t been funded enough to do the right tests, data analysis or regression tests on new software before it’s delivered, the report said.

In a passage omitted from the public version, the report said capabilities for the AIM-120 Advanced Medium-Range Air-to-Air Missile, or AMRAAM, that had been working on an earlier version of software broke when the development team tried to add capabilities for another weapon.

The F-35′s approach to software development in the Block 4 modernization effort, called Continuous Capability Development and Delivery, or C2D2, aims to develop, test and roll out software updates containing small batches of new capabilities or fixes to deficiencies every six months, instead of taking years to develop and deliver all the necessary capabilities at once.

But this approach has “proven unsustainable,” the report said, and the F-35 Joint Program Office extended that timeline of updates from every six months to once a year.

This process of incremental updates “often introduced stability problems,” or led to problems with other capabilities, the report said. This meant operational test units and field units in many cases were the ones to find the problems — sometimes significant operational deficiencies — with the software updates. Last year, operational test teams found problems with the F-35′s weapons, fusion communications and navigation, cybersecurity and targeting processes.

Grazier said this demonstrates the problem with fielding an aircraft whose design isn’t complete.
“If you’re going to have a software-driven design, you better make sure that original software is the 95% solution,” Grazier said. “Even with simple programs, when you start making changes in software in one place, you are very likely creating problems someplace else that were unanticipated. So you better make sure that your original version is pretty close to what you need — particularly before you start building hundreds and hundreds of them.”

Fick said that due to a holdup of funding in fiscal 2021, the program had to temporarily suspend most of the program’s Block 4 development, except for critical elements such as electronic warfare configurations. The arrival of funds in 2022 allowed the program to resume “the lion’s share” of Block 4 development, Fick said.

JPO spokeswoman Laura Seal said in a March 16 email the office “has delivered numerous new capabilities and sustainment improvements utilizing the C2D2 agile construct.”

“The JPO has taken feedback from our testers and customers and used it to improve the way we deliver software,” Seal said. “To this end, the F-35 enterprise has made significant progress in transforming into an agile delivery enterprise. Ultimately, the F-35 program delivers software on a warfighter-relevant timeline and our warfighters decide to take the software based on their review of the benefits of incorporating this software into their fleets.
  • The number of deficiencies has barely budged, because new problems keep popping up.
Last year, the DOT&E report tallied the number of open F-35 deficiencies at 871, 10 of which were Category 1 deficiencies, the most serious.
That improved in fiscal 2021 — but not by much. The F-35 had 845 open deficiencies, including six Category 1 deficiencies, at the end of the fiscal year. That number was not shared with the public until POGO released the controlled version of the report.

The report said F-35 program is working on addressing problems that have been identified during the system development and demonstration process. But the number of deficiencies isn’t shrinking significantly because new problems continue to be found.

By March 1, according to the latest figures from the JPO, that number had grown again to 873 total open deficiencies. That includes five Category 1B deficiencies, which can seriously affect mission readiness and keep a mission from being accomplished, although there are no open 1A deficiencies that pose a risk to the pilot’s life or a loss of the aircraft.

Seal said most of the new deficiency reports stem from issues that emerged in new capabilities added to the F-35. The JPO closed 171 deficiency reports in 2021, she said.

“Warfighters have assessed that acceptable mitigations exist for the remaining deficiencies,” Seal said. “Deficiency resolution is an ongoing effort, and deficiencies are resolved in concert with warfighters’ prioritization and resource allocation.”

She also said the potential effects of open deficiencies on missions or operations are documented in pilot manuals and training materials.
But Grazier said that the continual discovery of new problems means 2021′s decline to 845 open deficiencies shouldn’t be seen as a sign of success.

“It sounds like they’re making improvements, but really it’s one step forward and two-thirds of a step back,” Grazier said.
 

Rowbeartoe

NEW RECRUIT
Joined
Jan 22, 2023
Messages
3
Reactions
1 0 0
Country
USA
Location
USA
The F-35 may have had its hiccups but countries are now buying it other than just the U.S.


The link above shows a video of the F-35 compared to the F-16. With a low level demonstration, the F-35 doesn't look to shabby. It's attributes however are things you can't see at an airshow, sensor fusion, stealth, that helmet, and performance while caring weapons.
 
Top